— Project Summary

Queue ID
PRPA-21-11153
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Boulder, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPRPALBNL

125 MW hybrid in Boulder, CO · In queue since November 2021 · Proposed COD June 2027

125 MW

Capacity

1

Components

Solar

4y 4m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 7m

Impact Study25%
Queue EntryNov 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

CO

County

Boulder

Region

West

Developer

Utility

Platte River Power Authority

Entity

PRPA

Point of Interconnection

Longs Peak 230kV

Data Source

LBNL

No news available for this project.