BetaActiveSolarBatteryPRPALBNL
125 MW hybrid in Boulder, CO · In queue since November 2021 · Proposed COD June 2027
125 MW
Capacity
1
Components
Solar
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 7m
Impact Study25%
Queue EntryNov 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
CO
County
Boulder
Region
West
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Point of Interconnection
Longs Peak 230kV
Data Source
LBNL
No news available for this project.