— Project Summary

Queue ID
PRPA-21-11121
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryPRPALBNL

150 MW hybrid in Weld, CO · In queue since November 2021 · Proposed COD December 2025

150 MW

Capacity

1

Components

Solar

4y 4m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 1m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryNov 12, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Platte River Power Authority

Entity

PRPA

Point of Interconnection

Longs Peak 230kV

Data Source

LBNL

No news available for this project.