— Project Summary

Queue ID
PNM-IA-PNM-2024-04
Capacity
230 MW
Technology
Solar
Status
active
Location
Santa Fe, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarPNMLBNL

230 MW generation in Santa Fe, NM · In queue since June 2024 · Proposed COD July 2028

230 MW

Capacity

1

Components

Solar

1y 9m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Impact Study25%
Queue EntryJun 25, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

NM

County

Santa Fe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Norton - Diamond Tail 345 kV line

Data Source

LBNL