BetaActiveSolarBatteryPNMLBNL
225 MW hybrid in Otero, NM · In queue since June 2024 · Proposed COD November 2027
225 MW
Capacity
2
Components
Solar + Battery
1y 9m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Impact Study25%
Queue EntryJun 26, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-01
Technology
Solar150 MW · 67%
Battery75 MW · 33%
Project Details
State
NM
County
Otero
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Alamogordo 115 kV Substation
Data Source
LBNL
No news available for this project.