BetaActiveSolarBatteryPNMLBNL
250 MW hybrid in Bernalillo, NM · In queue since June 2024 · Proposed COD November 2028
250 MW
Capacity
2
Components
Solar + Battery
1y 9m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 5m
Impact Study25%
Queue EntryJun 26, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Technology
Solar150 MW · 60%
Battery100 MW · 40%
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Western Spirit 345 kV line
Data Source
LBNL
No news available for this project.