— Project Summary

Queue ID
PNM-IA-PNM-2023-30
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Santa Fe, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

250 MW hybrid in Santa Fe, NM · In queue since September 2023 · Proposed COD April 2029

250 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 7m

Impact Study25%
Queue EntrySep 29, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-01

Project Details

State

NM

County

Santa Fe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

New Substation on Clines Corners-Diamond Tail 345 kV Line

Data Source

LBNL