— Project Summary

Queue ID
PNM-IA-PNM-2023-28
Capacity
84.24 MW
Technology
Solar
Status
active
Location
Mckinley, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarPNMLBNL

84.24 MW generation in Mckinley, NM · In queue since September 2023 · Proposed COD June 2028

84.24 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 9m

Impact Study25%
Queue EntrySep 29, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

NM

County

Mckinley

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

New Substation on Ambrosia to Yah-Ta-Hey 115 kV Line

Data Source

LBNL

No news available for this project.