— Project Summary

Queue ID
PNM-IA-PNM-2023-22
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Santa Fe, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

200 MW hybrid in Santa Fe, NM · In queue since September 2023 · Proposed COD November 2028

200 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 2m

Impact Study25%
Queue EntrySep 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

NM

County

Santa Fe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

New substation on Clines Corners-Diamond Tail 345 kV line

Data Source

LBNL

No news available for this project.