BetaActiveSolarBatteryPNMLBNL
500 MW hybrid in San Juan, NM · In queue since September 2023 · Proposed COD December 2028
500 MW
Capacity
1
Components
Solar
2y 6m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 3m
Impact Study25%
Queue EntrySep 29, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NM
County
San Juan
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
New substation off the FW and WW 345 kV line
Data Source
LBNL
No news available for this project.