— Project Summary

Queue ID
PNM-IA-PNM-2023-21
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
San Juan, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

500 MW hybrid in San Juan, NM · In queue since September 2023 · Proposed COD December 2028

500 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

Impact Study25%
Queue EntrySep 29, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NM

County

San Juan

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

New substation off the FW and WW 345 kV line

Data Source

LBNL