150 MW storage in Valencia, NM · In queue since September 2023 · Proposed COD December 2026
150 MW
Capacity
1
Components
Battery
2y 6m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Impact Study25%
Queue EntrySep 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NM
County
Valencia
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Los Morros115 kV Substation
Data Source
LBNL
No news available for this project.