— Project Summary

Queue ID
PNM-IA-PNM-2023-13
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Valencia, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

100 MW hybrid in Valencia, NM · In queue since January 2023 · Proposed COD December 2026

100 MW

Capacity

1

Components

Solar

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 11m

Impact Study25%
Queue EntryJan 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

NM

County

Valencia

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Sun Ranch Switching Station

Data Source

LBNL

No news available for this project.