— Project Summary

Queue ID
PNM-IA-PNM-2023-09
Capacity
199 MW
Technology
Wind+Battery
Status
active
Location
Guadalupe, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveWindBatteryPNMLBNL

199 MW hybrid in Guadalupe, NM · In queue since December 2022 · Proposed COD May 2025

199 MW

Capacity

1

Components

Wind

3y 3m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 5m

Schedule

11 months past proposed COD

Impact Study25%
Queue EntryDec 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-01

Project Details

State

NM

County

Guadalupe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Guadalupe -Taiban 345 kV Line

Data Source

LBNL