199 MW hybrid in Guadalupe, NM · In queue since December 2022 · Proposed COD May 2025
199 MW
Capacity
1
Components
Wind
3y 3m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
11 months past proposed COD
Impact Study25%
Queue EntryDec 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-01
Project Details
State
NM
County
Guadalupe
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Guadalupe -Taiban 345 kV Line
Data Source
LBNL
No news available for this project.