— Project Summary

Queue ID
PNM-IA-PNM-2023-06
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Mckinley, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

199 MW hybrid in Mckinley, NM · In queue since December 2022 · Proposed COD December 2025

199 MW

Capacity

1

Components

Solar

3y 3m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

4 months past proposed COD

Impact Study25%
Queue EntryDec 30, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

NM

County

Mckinley

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Ambrosia 115 kV Substation

Data Source

LBNL

No news available for this project.