— Project Summary

Queue ID
PNM-IA-PNM-2023-04
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

200 MW hybrid in Bernalillo, NM · In queue since January 2023 · Proposed COD March 2027

200 MW

Capacity

1

Components

Solar

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 2m

Impact Study25%
Queue EntryJan 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Petroglyph to West Mesa 115 kV Line

Data Source

LBNL