200 MW hybrid in Bernalillo, NM · In queue since January 2023 · Proposed COD March 2027
200 MW
Capacity
1
Components
Solar
3y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 2m
Impact Study25%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Petroglyph to West Mesa 115 kV Line
Data Source
LBNL
No news available for this project.