— Project Summary

Queue ID
PNM-IA-PNM-2023-01
Capacity
250 MW
Technology
Wind
Status
active
Location
Cibola, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveWindPNMLBNL

250 MW generation in Cibola, NM · In queue since October 2022 · Proposed COD December 2025

250 MW

Capacity

1

Components

Wind

3y 5m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntryOct 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

NM

County

Cibola

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Ambrosia Lake - West Mesa 230 kV Line

Data Source

LBNL

No news available for this project.