— Project Summary

Queue ID
PNM-IA-PNM-2022-11
Capacity
100 MW
Technology
Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveBatteryPNMLBNL

100 MW storage in Bernalillo, NM · In queue since April 2022 · Proposed COD January 2024

100 MW

Capacity

1

Components

Battery

3y 11m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 9m

Schedule

27 months past proposed COD

Impact Study25%
Queue EntryApr 8, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-01-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Reeves Generating Station

Data Source

LBNL

No news available for this project.