— Project Summary

Queue ID
PNM-IA-PNM-2022-09
Capacity
375 MW
Technology
Solar+Battery
Status
active
Location
Mckinley, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

375 MW hybrid in Mckinley, NM · In queue since April 2022 · Proposed COD March 2025

375 MW

Capacity

2

Components

Solar + Battery

3y 11m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 11m

Schedule

13 months past proposed COD

Impact Study25%
Queue EntryApr 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-01

Technology
Solar250 MW · 67%
Battery125 MW · 33%
Project Details

State

NM

County

Mckinley

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Yah-Ta-Hey 115 kV Substation

Data Source

LBNL

No news available for this project.