BetaActiveSolarBatteryPNMLBNL
375 MW hybrid in Mckinley, NM · In queue since April 2022 · Proposed COD March 2025
375 MW
Capacity
2
Components
Solar + Battery
3y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
13 months past proposed COD
Impact Study25%
Queue EntryApr 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-01
Technology
Solar250 MW · 67%
Battery125 MW · 33%
Project Details
State
NM
County
Mckinley
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Yah-Ta-Hey 115 kV Substation
Data Source
LBNL
No news available for this project.