BetaActiveSolarPNMLBNL
49.9 MW generation in Grant, NM · In queue since April 2022 · Proposed COD June 2024
49.9 MW
Capacity
1
Components
Solar
3y 11m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 2m
Schedule
22 months past proposed COD
Impact Study25%
Queue EntryApr 8, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
NM
County
Grant
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Luna 115kV Line
Data Source
LBNL
No news available for this project.