— Project Summary

Queue ID
PNM-IA-PNM-2022-01
Capacity
600 MW
Technology
Hydro
Status
active
Location
San Juan, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveHydroPNMLBNL

600 MW generation in San Juan, NM · In queue since January 2022 · Proposed COD August 2028

600 MW

Capacity

1

Components

Hydro

4y 2m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 7m

Impact Study25%
Queue EntryJan 27, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Project Details

State

NM

County

San Juan

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

San Juan 345 kV Switching Station

Data Source

LBNL

No news available for this project.