BetaActiveSolarPNMLBNL
150 MW generation in Valencia, NM · In queue since July 2021 · Proposed COD July 2025
150 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Pending
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4 years
Schedule
9 months past proposed COD
In Study38%
Queue EntryJul 12, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-01
Project Details
State
NM
County
Valencia
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Huning Ranch Station
Data Source
LBNL
No news available for this project.