150 MW storage in Sandoval, NM · In queue since July 2021 · Proposed COD July 2024
150 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
21 months past proposed COD
Construction75%
Queue EntryJul 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
NM
County
Sandoval
Region
West
Developer
EsVolta Development
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Rio Puerco 115kV Substation
Data Source
LBNL
No news available for this project.