— Project Summary

Queue ID
PNM-IA-PNM-2021-12
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
De Baca, NM
Region
West
Developer
IA Status
IA Pending

BetaActiveSolarBatteryPNMLBNL

300 MW hybrid in De Baca, NM · In queue since July 2021 · Proposed COD June 2025

300 MW

Capacity

1

Components

Solar

4y 8m

In Queue

IA Pending

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

10 months past proposed COD

In Study38%
Queue EntryJul 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

NM

County

De Baca

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Taiban 345 kV Substation

Data Source

LBNL

No news available for this project.