100 MW hybrid in San Juan, NM · In queue since July 2021 · Proposed COD June 2025
100 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Pending
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 11m
Schedule
10 months past proposed COD
In Study38%
Queue EntryJul 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
NM
County
San Juan
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Bisti - 230 kV Line
Data Source
LBNL