— Project Summary

Queue ID
PNM-IA-PNM-2021-11
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
San Juan, NM
Region
West
Developer
IA Status
IA Pending

BetaActiveSolarBatteryPNMLBNL

100 MW hybrid in San Juan, NM · In queue since July 2021 · Proposed COD June 2025

100 MW

Capacity

1

Components

Solar

4y 8m

In Queue

IA Pending

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

10 months past proposed COD

In Study38%
Queue EntryJul 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

NM

County

San Juan

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Bisti - 230 kV Line

Data Source

LBNL