— Project Summary

Queue ID
PNM-IA-PNM-2021-09
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
NextEra Energy
IA Status
IA Executed

BetaActiveSolarBatteryPNMLBNL

150 MW hybrid in Bernalillo, NM · In queue since July 2021 · Proposed COD June 2025

150 MW

Capacity

1

Components

Solar

4y 8m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

10 months past proposed COD

Construction75%
Queue EntryJul 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

NextEra Energy

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Los Morros - West Mesa 115 kV Line

Data Source

LBNL

No news available for this project.