BetaActiveSolarPNMLBNL
200 MW generation in Guadalupe, NM · In queue since June 2021 · Proposed COD November 2024
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Pending
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Schedule
17 months past proposed COD
In Study38%
Queue EntryJun 11, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-01
Project Details
State
NM
County
Guadalupe
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Taiban- 345 kV Line
Data Source
LBNL
No news available for this project.