— Project Summary

Queue ID
PNM-IA-PNM-2021-08
Capacity
200 MW
Technology
Solar
Status
active
Location
Guadalupe, NM
Region
West
Developer
IA Status
IA Pending

BetaActiveSolarPNMLBNL

200 MW generation in Guadalupe, NM · In queue since June 2021 · Proposed COD November 2024

200 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Pending

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 5m

Schedule

17 months past proposed COD

In Study38%
Queue EntryJun 11, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-11-01

Project Details

State

NM

County

Guadalupe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Taiban- 345 kV Line

Data Source

LBNL