Pentstemon Solar
BetaActiveSolarBatteryPNMLBNL
199 MW hybrid in Santa Fe, NM · In queue since July 2021 · Proposed COD December 2024
199 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Schedule
16 months past proposed COD
Construction75%
Queue EntryJul 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
NM
County
Santa Fe
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Diamond Tail-Clines Corners
Data Source
LBNL
No news available for this project.