BetaActiveBatteryPNMLBNL
152.5 MW storage in Bernalillo, NM · In queue since June 2021 · Proposed COD April 2024
152.5 MW
Capacity
1
Components
Battery
4y 9m
In Queue
IA Pending
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 10m
Schedule
24 months past proposed COD
In Study38%
Queue EntryJun 4, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Central 115 kV Line
Data Source
LBNL