Zinnia Energy — Project Summary

Queue ID
PNM-IA-PNM-2021-01
Capacity
50 MW
Technology
Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
IA Status
IA Executed

Zinnia Energy

BetaActiveBatteryPNMLBNL

50 MW storage in Bernalillo, NM · In queue since June 2021 · Proposed COD June 2024

50 MW

Capacity

1

Components

Battery

4y 9m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

22 months past proposed COD

Construction75%
Queue EntryJun 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Reeves 115kV Line

Data Source

LBNL