Zinnia Energy
BetaActiveBatteryPNMLBNL
50 MW storage in Bernalillo, NM · In queue since June 2021 · Proposed COD June 2024
50 MW
Capacity
1
Components
Battery
4y 9m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
22 months past proposed COD
Construction75%
Queue EntryJun 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Reeves 115kV Line
Data Source
LBNL
No news available for this project.