BetaActiveSolarBatteryPNMLBNL
100 MW hybrid in Valencia, NM · In queue since October 2020 · Proposed COD November 2023
100 MW
Capacity
1
Components
Solar
5y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 1m
Schedule
29 months past proposed COD
Construction75%
Queue EntryOct 14, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
NM
County
Valencia
Region
West
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Sky Station
Data Source
LBNL
No news available for this project.