— Project Summary

Queue ID
PNM-IA-PNM-2020-21
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Valencia, NM
Region
West
Developer
NextEra Energy
IA Status
IA Executed

BetaActiveSolarBatteryPNMLBNL

100 MW hybrid in Valencia, NM · In queue since October 2020 · Proposed COD November 2023

100 MW

Capacity

1

Components

Solar

5y 5m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 1m

Schedule

29 months past proposed COD

Construction75%
Queue EntryOct 14, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2023-11-01

Project Details

State

NM

County

Valencia

Region

West

Developer

NextEra Energy

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Sky Station

Data Source

LBNL