Iris Del Sol
BetaActiveSolarBatteryPNMLBNL
76 MW hybrid in Otero, NM · In queue since October 2020 · Proposed COD May 2023
76 MW
Capacity
1
Components
Solar
5y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 7m
Schedule
35 months past proposed COD
Construction75%
Queue EntryOct 15, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-05-01
Project Details
State
NM
County
Otero
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Alamogordo-Holloman Airforce 115kV line
Data Source
LBNL