150 MW storage in Bernalillo, NM · In queue since September 2020 · Proposed COD January 2023
150 MW
Capacity
1
Components
Battery
5y 6m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 4m
Schedule
39 months past proposed COD
Construction75%
Queue EntrySep 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-01-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
AES Renewable Holdings
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Pajarito 345 kV Substation
Data Source
LBNL
No news available for this project.