Zinnia Storage — Project Summary

Queue ID
PNM-IA-PNM-2020-13
Capacity
100 MW
Technology
Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
IA Status
IA Executed

Zinnia Storage

BetaActiveBatteryPNMLBNL

100 MW storage in Bernalillo, NM · In queue since October 2020 · Proposed COD March 2023

100 MW

Capacity

1

Components

Battery

5y 5m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 5m

Schedule

37 months past proposed COD

Construction75%
Queue EntryOct 14, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-03-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Reeves Substation, 115 kV

Data Source

LBNL

No news available for this project.