Zinnia Storage
BetaActiveBatteryPNMLBNL
100 MW storage in Bernalillo, NM · In queue since October 2020 · Proposed COD March 2023
100 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 5m
Schedule
37 months past proposed COD
Construction75%
Queue EntryOct 14, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-03-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Reeves Substation, 115 kV
Data Source
LBNL
No news available for this project.