BetaActiveSolarBatteryPNMLBNL
90 MW hybrid in Mckinley, NM · In queue since May 2020 · Proposed COD June 2023
90 MW
Capacity
1
Components
Solar
5y 10m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 1m
Schedule
34 months past proposed COD
Impact Study25%
Queue EntryMay 18, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
NM
County
Mckinley
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Yah-Ta-Hey Substation
Data Source
LBNL
No news available for this project.