BetaActiveGasPNMLBNL
80 MW generation in San Juan, NM · In queue since January 2020 · Proposed COD May 2022
80 MW
Capacity
1
Components
Gas
6y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 4m
Schedule
48 months past proposed COD
Construction75%
Queue EntryJan 17, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2022-05-01
Project Details
State
NM
County
San Juan
Region
West
Developer
PNM _x0013_ Generation
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
San Juan Switching Station
Data Source
LBNL
No news available for this project.