BetaActiveSolarBatteryPNMLBNL
400 MW hybrid in Bernalillo, NM · In queue since January 2020 · Proposed COD September 2023
400 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 8m
Schedule
31 months past proposed COD
Construction75%
Queue EntryJan 17, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-09-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Bernalillo Solar West Mesa - Sandia 345 kV Line
Data Source
LBNL