— Project Summary

Queue ID
PNM-IA-PNM-2020-04
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Bernalillo, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryPNMLBNL

400 MW hybrid in Bernalillo, NM · In queue since January 2020 · Proposed COD September 2023

400 MW

Capacity

1

Components

Solar

6y 2m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 8m

Schedule

31 months past proposed COD

Construction75%
Queue EntryJan 17, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2023-09-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Bernalillo Solar West Mesa - Sandia 345 kV Line

Data Source

LBNL

No news available for this project.