— Project Summary

Queue ID
PNM-IA-PNM-2020-01
Capacity
145 MW
Technology
Wind
Status
active
Location
Guadalupe, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveWindPNMLBNL

145 MW generation in Guadalupe, NM · In queue since January 2020 · Proposed COD December 2021

145 MW

Capacity

1

Components

Wind

6y 2m

In Queue

IA Executed

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 11m

Schedule

53 months past proposed COD

Construction75%
Queue EntryJan 16, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2021-12-01

Project Details

State

NM

County

Guadalupe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Aragonne Wind Guadalupe 345 kV Station

Data Source

LBNL

No news available for this project.