145 MW generation in Guadalupe, NM · In queue since January 2020 · Proposed COD December 2021
145 MW
Capacity
1
Components
Wind
6y 2m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 11m
Schedule
53 months past proposed COD
Construction75%
Queue EntryJan 16, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
NM
County
Guadalupe
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Aragonne Wind Guadalupe 345 kV Station
Data Source
LBNL