— Project Summary

Queue ID
PNM-IA-PNM-2019-18
Capacity
100 MW
Technology
Battery
Status
suspended
Location
Bernalillo, NM
Region
West
Developer
IA Status
Suspended

BetaSuspendedBatteryPNMLBNL

100 MW storage in Bernalillo, NM · In queue since April 2019 · Proposed COD March 2022

100 MW

Capacity

1

Components

Battery

6y 11m

In Queue

Suspended

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 11m

Suspended38%
Queue EntryApr 22, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-03-01

Project Details

State

NM

County

Bernalillo

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Oso Negro West Mesa 115 kV Line

Data Source

LBNL