100 MW storage in Bernalillo, NM · In queue since April 2019 · Proposed COD March 2022
100 MW
Capacity
1
Components
Battery
6y 11m
In Queue
Suspended
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 11m
Suspended38%
Queue EntryApr 22, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-03-01
Project Details
State
NM
County
Bernalillo
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Oso Negro West Mesa 115 kV Line
Data Source
LBNL
No news available for this project.