BetaActiveWindPNMLBNL
80 MW generation in Torrance, NM · In queue since April 2019 · Proposed COD September 2020
80 MW
Capacity
1
Components
Wind
6y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1y 5m
Schedule
68 months past proposed COD
In Study38%
Queue EntryApr 23, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-09-01
Project Details
State
NM
County
Torrance
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Clines Corners 345 kV Switching Station
Data Source
LBNL
No news available for this project.