— Project Summary

Queue ID
PNM-IA-PNM-2019-08
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Mckinley, NM
Region
West
Developer
RWE Solar Dev
IA Status
IA Executed

BetaActiveSolarBatteryPNMLBNL

125 MW hybrid in Mckinley, NM · In queue since April 2019 · Proposed COD December 2022

125 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 8m

Schedule

40 months past proposed COD

Construction75%
Queue EntryApr 22, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

NM

County

Mckinley

Region

West

Developer

RWE Solar Dev

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Yah-Ta-Hey _x0013_ Pitt Midway Line

Data Source

LBNL

No news available for this project.