96 MW hybrid in Santa Fe, NM · In queue since April 2019 · Proposed COD December 2021
96 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 8m
Schedule
53 months past proposed COD
Construction75%
Queue EntryApr 23, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
NM
County
Santa Fe
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Randho Viejo Zia/Rodeo _x0013_ El Dorado Line
Data Source
LBNL