Affordable Solar — Project Summary

Queue ID
PNM-IA-PNM-2018-05
Capacity
190 MW
Technology
Solar+Battery
Status
active
Location
Rio Arriba, NM
Region
West
Developer
IA Status
IA Executed

Affordable Solar

BetaActiveSolarBatteryPNMLBNL

190 MW hybrid in Rio Arriba, NM · In queue since July 2018 · Proposed COD December 2021

190 MW

Capacity

2

Components

Solar + Battery

7y 8m

In Queue

IA Executed

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 5m

Schedule

53 months past proposed COD

Construction75%
Queue EntryJul 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2021-12-01

Technology
Solar150 MW · 79%
Battery40 MW · 21%
Project Details

State

NM

County

Rio Arriba

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

PNM Jicarilla 345 kV Switching Station near Dulce

Data Source

LBNL