BetaSuspendedSolarBatteryPNMLBNL
150 MW hybrid in Mckinley, NM · In queue since July 2018 · Proposed COD June 2021
150 MW
Capacity
2
Components
Solar + Battery
7y 8m
In Queue
Suspended
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 11m
Suspended38%
Queue EntryJul 27, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-06-01
Technology
Solar75 MW · 50%
Battery75 MW · 50%
Project Details
State
NM
County
Mckinley
Region
West
Developer
NTUA
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
New 115/24.9 kV sub on PNM Yah-Ta-Hey-Pitt Midway115 kV Line
Data Source
LBNL
No news available for this project.