— Project Summary

Queue ID
PNM-IA-PNM-2018-02
Capacity
150 MW
Technology
Solar+Battery
Status
suspended
Location
Mckinley, NM
Region
West
Developer
NTUA
IA Status
Suspended

BetaSuspendedSolarBatteryPNMLBNL

150 MW hybrid in Mckinley, NM · In queue since July 2018 · Proposed COD June 2021

150 MW

Capacity

2

Components

Solar + Battery

7y 8m

In Queue

Suspended

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 11m

Suspended38%
Queue EntryJul 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-06-01

Technology
Solar75 MW · 50%
Battery75 MW · 50%
Project Details

State

NM

County

Mckinley

Region

West

Developer

NTUA

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

New 115/24.9 kV sub on PNM Yah-Ta-Hey-Pitt Midway115 kV Line

Data Source

LBNL

No news available for this project.