BetaActiveSolarPNMLBNL
95.6 MW generation in San Juan, NM · In queue since October 2017 · Proposed COD October 2022
95.6 MW
Capacity
1
Components
Solar
8y 5m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5 years
Schedule
42 months past proposed COD
Construction75%
Queue EntryOct 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2022-10-01
Project Details
State
NM
County
San Juan
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
PNM Technical Services San Juan Gen Station
Data Source
LBNL
No news available for this project.