— Project Summary

Queue ID
PNM-IA-PNM-2017-14
Capacity
236.3 MW
Technology
Gas
Status
active
Location
San Juan, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveGasPNMLBNL

236.3 MW generation in San Juan, NM · In queue since October 2017 · Proposed COD October 2022

236.3 MW

Capacity

1

Components

Gas

8y 5m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

5 years

Schedule

42 months past proposed COD

Construction75%
Queue EntryOct 27, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2022-10-01

Project Details

State

NM

County

San Juan

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

PNM Technical Services San Juan Gen Station

Data Source

LBNL

No news available for this project.