BetaActiveSolarBatteryPNMLBNL
500 MW hybrid in San Juan, NM · In queue since October 2017 · Proposed COD December 2020
500 MW
Capacity
2
Components
Solar + Battery
8y 5m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 2m
Schedule
65 months past proposed COD
Construction75%
Queue EntryOct 26, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2020-12-01
Technology
Solar400 MW · 80%
Battery100 MW · 20%
Project Details
State
NM
County
San Juan
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
San Juan Solar 1 San Juan Gen Station
Data Source
LBNL
No news available for this project.