— Project Summary

Queue ID
PNM-IA-PNM-2017-11
Capacity
74.9 MW
Technology
Solar+Battery
Status
active
Location
Torrance, NM
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPNMLBNL

74.9 MW hybrid in Torrance, NM · In queue since June 2017 · Proposed COD June 2020

74.9 MW

Capacity

2

Components

Solar + Battery

8y 9m

In Queue

System Impact Study

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

3 years

Schedule

71 months past proposed COD

Impact Study25%
Queue EntryJun 5, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-01

Technology
Solar49.9 MW · 67%
Battery25 MW · 33%
Project Details

State

NM

County

Torrance

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

Britton 115 kV Substation

Data Source

LBNL

No news available for this project.