BetaActiveSolarBatteryPNMLBNL
74.9 MW hybrid in Torrance, NM · In queue since June 2017 · Proposed COD June 2020
74.9 MW
Capacity
2
Components
Solar + Battery
8y 9m
In Queue
System Impact Study
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3 years
Schedule
71 months past proposed COD
Impact Study25%
Queue EntryJun 5, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-06-01
Technology
Solar49.9 MW · 67%
Battery25 MW · 33%
Project Details
State
NM
County
Torrance
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Britton 115 kV Substation
Data Source
LBNL