NMRD Data Center IV
BetaActiveSolarPNMLBNL
140 MW generation in Sandoval, NM · In queue since January 2017 · Proposed COD November 2022
140 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5y 10m
Schedule
41 months past proposed COD
Construction75%
Queue EntryJan 31, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2022-11-01
Project Details
State
NM
County
Sandoval
Region
West
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
Rio Puerco Station
Data Source
LBNL
News & Articles (1)Beta