NMRD Data Center IV — Project Summary

Queue ID
PNM-IA-PNM-2017-09
Capacity
50 MW
Technology
Solar
Status
active
Location
Santa Fe, NM
Region
West
Developer
IA Status
IA Executed

NMRD Data Center IV

BetaActiveSolarPNMLBNL

50 MW generation in Santa Fe, NM · In queue since January 2017 · Proposed COD November 2022

50 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

5y 10m

Schedule

41 months past proposed COD

Construction75%
Queue EntryJan 31, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2022-11-01

Project Details

State

NM

County

Santa Fe

Region

West

Developer

Utility

Public Service Company of New Mexico

Entity

PNM

Point of Interconnection

BA-ZIA 115 kV Line

Data Source

LBNL