10 MW generation in Cibola, NM · In queue since January 2017 · Proposed COD August 2021
10 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
4y 7m
Schedule
57 months past proposed COD
Construction75%
Queue EntryJan 26, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2021-08-01
Project Details
State
NM
County
Cibola
Region
West
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Point of Interconnection
On the Bluewater-West Mesa 115 kV Line near San Fidel
Data Source
LBNL