— Project Summary

Queue ID
PNM-IA-PNM-2016-02
Capacity
402 MW
Technology
Wind
Status
active
Location
Torrance, NM
Region
West
Developer
Pattern Energy Wind Development
IA Status
IA Executed

BetaActiveWindPNMLBNL

402 MW generation in Torrance, NM · In queue since May 2016 · Proposed COD September 2020

402 MW

Capacity

1

Components

Wind

9y 10m

In Queue

IA Executed

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

4y 4m

Schedule

68 months past proposed COD

Construction75%
Queue EntryMay 5, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2020-09-01

Project Details

State

NM

County

Torrance

Region

West

Developer

Pattern Energy Wind Development

Utility

Public Service Company of New Mexico

Entity

PNM

Data Source

LBNL

No news available for this project.