BetaActiveWindPNMLBNL
402 MW generation in Torrance, NM · In queue since May 2016 · Proposed COD September 2020
402 MW
Capacity
1
Components
Wind
9y 10m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
4y 4m
Schedule
68 months past proposed COD
Construction75%
Queue EntryMay 5, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2020-09-01
Project Details
State
NM
County
Torrance
Region
West
Developer
Pattern Energy Wind Development
Utility
Public Service Company of New Mexico
Entity
PNM
Data Source
LBNL